After successful implementation of MTBF in Pilot Ministries (i.e. Ministry of Health and Ministry of Population Welfare), MTBF is now being rolled out to other Ministries. One of the key Roll-out Ministries for MTBF 2006-09 includes Ministry of Education (MOE).

The Letter of Induction was issued to the Ministry on 23rd September 2005. Since then, following milestones of MTBF implementation process in MoE have been achieved.

PROGRESS

DATE

Meeting Held with Secretary MoE 10th September 2005
Establishment of MTBF Cell MoE 16th September 2005
Letter of Induction issued to MoE 23rd September 2005
Core team of MoE nominated October 5th 2005
Meeting held with DG FDE 2nd week of October 2005
MTBF Cell established in FDE 2nd week of October 2005
Core team sensitization meeting held 20th October 2005
Finalization of FDE specific MTBF forms 22nd October 2005
MTBF sensitization meetings for heads of education institutions 24-29 October 2005
MTBF training workshops of DDOs and budget preparing officials of  federal Education Institutions

12-21 November 2005

Handholding of FDE staff and DDOs/BPOs of Federal Education Institutions 15 November-15 December 2005
Completion of MTBF budget submissions of 7 F.G. Colleges and 19 Model Colleges 7th December 2005
Completion of MTBF budget submissions of 379 F.G. schools 15th December 2005

 

  • MTBF team started visiting the spending units of current budgets otrher than FDE on 2nd December 2005. All the DDOs were visited in person or in collective meetings and were imparted training in MTBF approach and techniques
     
  • Budgets of 4o5 Federal Education Institutions working under FDE have been completed and submitted to MoE by 28th December 2005
     
  • Budgets of 25 spending units other than FDE have been received on MTBF format
     
  • In the following Table, a budget status summary is presented. This provides number of budgets received and processed  together with number of spending units visited / contacted so far:

 

Budget Status Summary

DESCRIPTION

NO.

Total No. of Budgets in 2005-06 (including Grants / Single liners)

473

MTBF budgets officially submitted to MOE

405

MTBF budgets (draft versions) submitted

25

Initial Review of Estimates carried out by MTBF Cell

430

Budgets entered in Budgeting Module

430

Budgets expected to be received in a week’s time

43

 ACTIVITIES PLANNED

  • Preparatory work for Ministry Strategic review is under way.  Core team members would be involved for their guidance and vision. First version of MSR Report would ready for discussion by January/ February 2006
     

  • MTBF Cell has already been established in the Projects Wing of MoE and work on Development Budget has started
     

  • For Development projects, close coordination is maintained with DEA (Projects Wing) and DEA (Policy and Planning Wing)
     

  • Coordination with SO (F&A), Other MoE officials and FA Organization would continue to review, consolidate, finalize and approve the MTBF estimates 2006-09