After successful
implementation of MTBF in Pilot Ministries (i.e. Ministry of Health and
Ministry of Population Welfare), MTBF is now being rolled out to other
Ministries. One of the key Roll-out Ministries for MTBF 2006-09 includes
Ministry of Education (MOE).
The Letter of
Induction was issued to the Ministry on 23rd September 2005.
Since then, following milestones of MTBF implementation process in MoE
have been achieved.
|
PROGRESS |
DATE |
|
Meeting Held with Secretary
MoE |
10th
September 2005 |
|
Establishment of MTBF Cell MoE |
16th
September 2005 |
|
Letter of Induction issued to
MoE |
23rd
September 2005 |
|
Core team of MoE nominated |
October
5th 2005 |
|
Meeting held with DG FDE |
2nd
week of October 2005 |
|
MTBF Cell established in FDE |
2nd
week of October 2005 |
|
Core team sensitization
meeting held |
20th
October 2005 |
|
Finalization of FDE specific
MTBF forms |
22nd
October 2005 |
|
MTBF sensitization meetings
for heads of education institutions |
24-29
October 2005 |
|
MTBF training workshops of
DDOs and budget preparing officials of federal
Education Institutions |
12-21 November
2005 |
|
Handholding of FDE staff and
DDOs/BPOs of Federal Education Institutions |
15
November-15 December 2005 |
|
Completion of MTBF budget
submissions of 7 F.G. Colleges and 19 Model Colleges |
7th
December 2005 |
|
Completion of MTBF budget
submissions of 379 F.G. schools |
15th
December 2005 |
-
MTBF team
started visiting the spending units of current budgets otrher
than FDE on 2nd December 2005. All the DDOs were
visited in person or in collective meetings and were imparted
training in MTBF approach and techniques
-
Budgets of 4o5
Federal Education Institutions working under FDE have been
completed and submitted to MoE by 28th December 2005
-
Budgets of 25
spending units other than FDE have been received on MTBF format
-
In the
following Table, a budget status summary is presented. This
provides number of budgets received and processed together with
number of spending units visited / contacted so far:
Budget Status Summary
|
DESCRIPTION |
NO. |
|
Total No.
of Budgets in 2005-06 (including Grants / Single liners)
|
473 |
|
MTBF
budgets officially submitted to MOE |
405 |
|
MTBF
budgets (draft versions) submitted |
25 |
|
Initial
Review of Estimates carried out by MTBF Cell
|
430 |
|
Budgets
entered in Budgeting Module |
430 |
|
Budgets
expected to be received in a week’s time |
43 |
ACTIVITIES
PLANNED
-
Preparatory work for Ministry Strategic review is under way.
Core team members would be involved for their guidance and
vision. First version of MSR Report would ready for discussion
by January/ February 2006
-
MTBF
Cell has already been established in the Projects Wing of MoE
and work on Development Budget has started
-
For
Development projects, close coordination is maintained with DEA
(Projects Wing) and DEA (Policy and Planning Wing)
-
Coordination with SO (F&A), Other MoE officials and FA
Organization would continue to review, consolidate, finalize and
approve the MTBF estimates 2006-09
|